I-675 Pedestrian Bridge Project Schedule (as of 12/20/2008)

Milestone

Commitment Date

Authorize Design Consultant

May 2010

Preliminary Engineering Starts

2010

Preliminary Engineering Study Submitted

February 2011

Preliminary Engineering Study Complete

March 2011

Stage 1 Plans Submitted

November 2011

Stage 1 Plans Complete

December 2011

Environmental Document Approved (CE-2)

January 2012

Stage 2 Plans Submitted

June 2012

Stage 2 Plans Complete

July 2012

Final Right of Way Plans Submitted

August 2012

Right of Way Authorized

September 2012

Stage 3 Plans Submitted

November 2012

Stage 3 Plans Complete

December 2012

Project Right of Way Acquisition Starts

2013

Tracings Submitted

April 2013

Tracings Approved

May 2013

Clear Right of Way

May 2013

District Right of Way Certification

May 2013

Plan Package to Central Office

June 2013

Sale Date

August 2013

Award Date

September 2013

Construction Starts

2013 (fiscal year 2014)

 