I-675 Pedestrian Bridge Project Schedule (as of 12/20/2008) |
|
Milestone |
Commitment Date |
|
Authorize Design Consultant |
May 2010 |
|
Preliminary Engineering Starts |
2010 |
|
Preliminary Engineering Study Submitted |
February 2011 |
|
Preliminary Engineering Study Complete |
March 2011 |
|
Stage 1 Plans Submitted |
November 2011 |
|
Stage 1 Plans Complete |
December 2011 |
|
Environmental Document Approved (CE-2) |
January 2012 |
|
Stage 2 Plans Submitted |
June 2012 |
|
Stage 2 Plans Complete |
July 2012 |
|
Final Right of Way Plans Submitted |
August 2012 |
|
Right of Way Authorized |
September 2012 |
|
Stage 3 Plans Submitted |
November 2012 |
|
Stage 3 Plans Complete |
December 2012 |
|
Project Right of Way Acquisition Starts |
2013 |
|
Tracings Submitted |
April 2013 |
|
Tracings Approved |
May 2013 |
|
Clear Right of Way |
May 2013 |
|
District Right of Way Certification |
May 2013 |
|
Plan Package to Central Office |
June 2013 |
|
Sale Date |
August 2013 |
|
Award Date |
September 2013 |
|
Construction Starts |
2013 (fiscal year 2014) |