Five Year Capital Improvement Projects

activecapimprov2012

1) Beavercreek Signals Interconnect Project (Phase 2); PID# 86976

Project Description: This project will expand the closed-loop fiber optic signal system.  Work includes installation of fiber optic cable along various routes in the City of Beavercreek.  The project also generally includes the following:

Funding:

FEDERAL

STATE (OPWC)

LOCAL

TOTAL

Engineering

$0

$0

$238,000 (100%)

$238,000

Construction

$1,726,000 (77%)

$515,558 (23%)

$0

$2,241.558

Status: The project engineering is ongoing with a current completion in Summer 2012.  Construction is currently scheduled to begin in Fall 2012.



2) Col. Glenn Highway @ Grange Hall Road Widening Project; PID# 84434

Project Description: The project generally consists of the following components:

Funding:

FEDERAL

LOCAL

TOTAL

Engineering

$67,000 (93%)

$5,000 (7%)

$72,000

Right-of-Way

$99,000 (90%)

$11,000 (10%)

$110,000

Construction

$407,940 (90%)

$45,330 (10%)

$453,270

Status: Construction is currently scheduled to begin in Spring 2012.



3) Zink Road Extension Project

Project Description: The project generally consists of the completion of the extension of Zink Road between Col. Glenn Highway and Germany Lane.

Funding: Construction = $132,000 (Local/Total)

Status:  The project is currently scheduled to be constructed in 2013.



4) Grange Hall Road Streetscape Project; PID# 91175

Project Description: The project involves the enhancement of the intersection of Grange Hall Road and Pentagon Boulevard.  The project generally consists of the following components:

Funding:

FEDERAL

LOCAL

TOTAL

Engineering

$0

$35,000 (100%)

$35,000

Construction

$272,000 (80%)

$68,000 (20%)

$340,000

Status: The project design and environmental analysis are currently scheduled to be completed by the end of 2013.  Construction is currently scheduled to begin in Summer 2014.



5) Park Overlook Roundabout

Project Description: The project generally consists of the reconstruction of the intersection of Park Overlook Drive and Royal Gateway Drive by reconstructing the intersection with a roundabout.

Funding:

LOCAL/TOTAL

Engineering

$16,531

Construction

$263,000


Status: The project is currently in the design phase.  Design is currently scheduled to be completed in the Fall of 2012.  The project is scheduled to be constructed in the Summer of 2014.



6) North Fairfield Road @ I-675 Widening Project; PID# 85167

Project Description: The project generally consists of the following components:

Funding:

FEDERAL

LOCAL

TOTAL

IMS/Environmental

$91,800 (90%)

$10,200 (10%)

$102.000

Engineering

$81,900 (90%)

$9,100 (10%)

$91,000

Construction

$816,300 (90%)

$90,700 (10%)

$907,000

Status: The project design is complete.  The project is currently scheduled to be constructed in 2012.



7) I-675 Pedestrian Bridge Project; PID# 84238

Project Description: The project generally consists of the construction of a multi-purpose pedestrian/bicycle bridge across I-675 at a point west of NFR in Beavercreek to a point by Center Park Boulevard in Fairborn.

Funding:

FEDERAL

LOCAL

TOTAL

Engineering

$192,000 (80%)

$48,200 (20%)

$240,000

Right-of-Way

$16,000 (80%)

$4,000 (20%)

$20,000

Construction

$2,200,000 (80%)

$550,000 (20%)

$2,750,000

Status: The design of the project is currently scheduled to begin in the Summer of 2012 with Right-of-Way acquisition commencing in 2013.  Construction is currently scheduled to begin in Spring 2014.



8 ) North Fairfield Road @ I-675 Bridge Widening; PID# 77920

Project Description: The project consists of minor pavement rehabilitation on I-675 between the Grange Hall Road interchange in Beavercreek and the SR 235 interchange in Fairborn.  This project will also generally include the following work on the North Fairfield Road bridge over I-675:

Funding:

FEDERAL

STATE

LOCAL

TOTAL

Environmental/Prelim. Engineering

$457,912.80 (90%)

$50,879.20 (10%)

$0 (0%)

$508,792

Engineering

$363,444.30 (90%)

$40,382.70 (10%)

$0 (0%)

$403,827

Construction

$14,397,350 (89%)

$1,194,150 (7%)

$660,000 (4%)

$16,251,500

Status: Environmental analysis for the project has been completed.  The project is currently in the design phase with design currently scheduled to be completed in the Summer of 2013.  Construction is currently scheduled to begin in the Fall of 2013.



9) New Germany-Trebein Road @ North Fairfield Road Safety Improvements; OPWC# CK150

Project Description: The project generally consists of the following components:

Funding:

STATE (OPWC)

LOCAL

TOTAL

Engineering

$25,900 (74%)

$9,100 (26%)

$35,000

Construction

$284,900 (74%)

$100,100 (26%)

$385,000

Status: The project is currently in the design phase of the project.  The design is currently scheduled to be completed in the Summer of 2012.  Construction is currently scheduled to begin in the early Fall of 2012.



10) New Germany-Trebein Road Widening Project; PID# 84222

Project Description: The project is a widening project that generally consists of the following components:

Funding:

FEDERAL

LOCAL

TOTAL

Engineering

$0 (0%)

$95,000 (100%)

$95,000

Right-of-Way

$0 (0%)

$105,000 (100%)

$105,000

Construction

$1,100,000 (80%)

$275,000 (20%)

$1, 375,000

Status: The design of the project is currently ongoing and is currently scheduled to be completed in late 2012.  Right-of-Way acquisition is currently scheduled to commence in 2012.  Construction is currently scheduled to begin in Spring 2013.



11) Grange Hall Road Widening Project; PID# 88315

Project Description: The project involves the widening of Grange Hall Road from Kemp Road to Gardenview Drive/Lujon Drive.  The project generally consists of the following components:

Funding:

FEDERAL

LOCAL

TOTAL

Engineering

$0 (0%)

$178,000 (100%)

$178,000

Right-of-Way

$150,000 (61%)

$97,000 (39%)

$247,000

Construction

$1,402,500 (75%)

$467,500 (25%)

$1,870,000

Status: The project is currently in the design phase.  Design is currently scheduled to be ongoing through the end of 2014.  Right-of-way acquisition is currently scheduled to take place between Summer 2013 and the end of 2014.  Construction is currently scheduled to begin in the Summer of 2015.



12) Lillian Lane Extension Project

Project Description: The project generally consists of the extension of Lillian Lane south approximately 1000 feet from Westminster Drive to Lakeview Drive.

Funding:

LOCAL/TOTAL

Engineering

$24,650

Right-of-Way

$100,000

Construction

$400,000

Status: The project is currently under design with design currently scheduled to be completed in Spring 2012.  Right-of-Way acquisition is currently scheduled to take place during 2012.  The project is currently scheduled to begin construction in 2013.



13) Price Drainage Project (Kemp Road)

Project Description: The project generally consists of Phase I for additional storm sewer and drainage problem corrections for the surrounding neighborhood.  This project is located along Kemp Road in the vicinity of Tulane Drive.

Funding: Construction = $123,000 (Local/Total)

Status: The project is currently scheduled for construction in 2012.



14) Hanes Road @ Kemp Road Widening and Signalization Project; PID# 84228

Project Description: The project generally consists of the following components:

Funding:

FEDERAL

LOCAL

TOTAL

Engineering

$0 (0%)

$45,000 (100%)

$45,000

Right-of-Way

$0 (0%)

$10,000 (100%)

$10,000

Construction

$386,100 (78%)

$108,900 (22%)

$495,000

Status: Design and right-of-way acquisition for the project are complete.  Construction is currently scheduled to begin in Spring 2012.



15) Hanes Road Bridge Replacement Project; PID# 91688

Project Description: The project consists of replacement of the deficient bridge on Hanes Road located approximately 100 feet south of Kings Gate Boulevard.  The project generally consists of the following components:

Funding:

FEDERAL

LOCAL

TOTAL

Engineering

$0 (0%)

$61,000 (100%)

$61,000

Right-of-Way

$0 (0%)

$20,000 (100%)

$20,000

Construction

$315,840 (80%)

$78,760 (20%)

$394,600

Status: The project is currently in the environmental and design phase.  Environmental analysis is currently scheduled to be completed in the Fall of 2012.  Design and Right-of-Way acquisition are currently scheduled to be completed in the end of 2013.  Construction is currently scheduled to begin in 2014.



16) Sunnyside Drive Drainage Improvement Project

Project Description: This project is a generally consists of drainage improvements along Sunnyside Drive to correct existing drainage problems.

Funding: Construction = $30,000 (Local/Total)

Status: The project is currently scheduled to begin construction in 2012.



17) Dayton-Xenia Road @ Grange Hall Road Streetscape Project; PID# 88317

Project Description: The project is the enhancement of the Dayton-Xenia Road at Grange Hall Road intersection that generally consists of the following components:

Funding:

FEDERAL

LOCAL

TOTAL

Engineering

$0 (0%)

$46,000 (100%)

$46,000

Right-of-Way

$0 (0%)

$20,000 (100%)

$20,000

Construction

$297,000 (75%)

$99,000 (25%)

$396,000

Status: Design is currently scheduled to commence between 2013 and 2014.  Construction is currently scheduled to begin in Spring 2015.



18) Lantz Road Extension Project

Project Description: The project generally consists of the extension of Lantz Road from North Fairfield Road west approximately 300 feet.

Funding:

LOCAL/TOTAL

Engineering

$50,000

Construction

$100,000

Status: The project is currently in the design phase with design currently scheduled to be completed in the Summer of 2012.  Construction is currently scheduled to begin in 2012.



19) Grange Hall Road Bridge Rehabilitation Project; PID# 91685

Project Description: The bridge rehabilitation project is for the bridge over Little Beaver Creek located just north of the Grange Hall Road and Patterson Road intersection.  The project generally consists of the following components:

Funding:

FEDERAL

LOCAL

TOTAL

Engineering

$0 (0%)

$76,900 (100%)

$76,900

Construction

$324,720 (78%)

$91,180 (22%)

$415,900

Status: The project is currently in the design phase.  Design for the project is currently scheduled to be completed in 2012.  Construction is currently scheduled to begin in 2014.



20) Patterson Road Storm Sewer Improvements

Project Description: The project generally consists of improvements to the existing culvert on Patterson Road just east of Grange Hall Road and drainage improvements along Richfield Center.

Funding: Construction = $40,000 (Local/Total)



21) 2011 Bridge Sealing Project

Project Description: The project generally consists of the patching and sealing of the MSE walls and parapet walls with epoxy urethane sealer of the following bridges:

Funding: Construction = $200,000 (Local/Total)

Status: The project was awarded in the Fall of 2011.  Due to weather restrictions for the sealant, construction will begin in the Spring of 2012.  Construction is currently scheduled to last until early Summer 2012.



22) Beaver Vu Drive Signal Project; PID# 86974

Project Description: The project generally consists of the following components:

Funding:

FEDERAL

LOCAL

TOTAL

Engineering

$0 (0%)

$15,000 (100%)

$15,000

Construction

$132,000 (80%)

$33,000 (20%)

$165,000

Status: The project is currently under construction.  Construction is currently scheduled to be completed in 2012.



23) Factory Road @ Richmar Drive Widening Project; PID# 84232

Project Description: This widening project generally consists of the following components:

Funding:

FEDERAL

LOCAL

TOTAL

Engineering

$0 (0%)

$50,500 (100%)

$50,500

Right-of-Way

$0 (0%)

$22,000 (100%)

$22,000

Construction

$450,450 (78%)

$127,050 (22%)

$577,500

Status: The design of this improvement has begun and is currently scheduled to be completed in late 2012.  Right-of-Way acquisition is currently scheduled to take place between Summer 2012 through late 2013.  Construction is currently scheduled to begin in late Spring 2013.



24) North Fairfield Road Widening Project;  PID# 83316

Project Description: The project is a road widening project that generally consists of the following components:

Funding:

FEDERAL

LOCAL

TOTAL

Engineering

$0 (0%)

$240,000 (100%)

$240,000

Right-of-Way

$0 (0%)

$180,000 (100%)

$180,000

Construction

$1,237,500 (75%)

$412,500 (25%)

$1,650,000

Status: The project is currently in the environmental analysis and design phase of the project.  Environmental analysis is currently scheduled to be completed in Summer 2013.  Design is currently scheduled to be competed in the beginning of 2015.  Right-of-Way acquisition is currently scheduled to take place between Summer 2013 and the end of 2014.  Construction is currently scheduled to begin in 2015.



25) US 35 @ Factory Road Safety Improvement Project; PID# 91463

Project Description: The project consists of signal upgrades to the intersection that generally consists of the following components:

Funding:

FEDERAL

LOCAL

TOTAL

Engineering

$58,050 (100%)

$0 (0%)

$58,050

Construction

$255,420 (100%)

$0 (0%)

$255,420

Status: The project is currently in the design phase with design currently scheduled to be completed in Summer 2012.  Construction is currently scheduled to begin in the Fall of 2012.



26) US 35 Corridor Improvements Project; PID# 80468

Project Description: In 2004, the Miami Valley Regional Planning Commission (MVRPC) in cooperation with ODOT completed the Greene US 35 Corridor Study to recommend a strategy to convert the section of US 35 between the North Fairfield Road interchange and the Xenia Bypass to a limited access facility.  The current project, GRE-35-4.26, focuses on the recommendations of the Corridor Study following ODOT’s Project Development Process (PDP).  The PDP provides a framework for the decision making to take a project from the planning stages to construction.  Additional information can be obtained at the MVRPC website (www.mvrpc.org/projects/us-35/gre).

Funding:

FEDERAL/STATE

LOCAL (MVRPC)

UNFUNDED

TOTAL

Engineering

$6,244.190.20 (70%)

$321,870.80 (4%)

$2,295,120 (26%)

$8,861,181

Right-of-Way

—-

—-

$5,300,000 (100%)

$5,300,000

Construction

—-

—-

$98,424,500 (100%)

$98,242,500

Status: The project is currently in the environmental analysis and design phases.  Environmental analysis and design are currently scheduled to be completed in 2013.  Please see additional information on MVRPC’s website for current timetables for Right-of-Way and Construction.  Please be advised that these dates are likely to change due to the Right-of-Way and Construction portions of the project currently being unfunded.



27) Indian Ripple Road Safety Improvements; PID# 92554

Project Description: The project includes safety improvements to the Indian Ripple Road corridor from County Line Road through the Indian Ripple Road/I-675 interchange.  These improvements generally consist of the following:

Funding:

FEDERAL

LOCAL

TOTAL

Engineering

$85,726 (90%)

$9,525 (10%)

$95,251

Construction

$270,900 (90%)

$30,100 (10%)

$301,000

Status: The project is currently in the planning stages.  Currently, the Interchange Modification Study (IMS) is being completed with the current scheduled completion date in the Summer of 2012.  Design is currently scheduled to take place between 2013 and 2014.  Construction is currently scheduled to begin in the Summer of 2014.



28) I-675 @ Indian Ripple Road Enhancement Project; PID# 86973

Project Description: The project generally consists of the following components:

Funding:

FEDERAL

LOCAL

TOTAL

Engineering

$0 (0%)

$50,000 (100%)

$50,000

Construction

$297,000 (50%)

$297,000 (50%)

$594,000

Status: Design work is currently scheduled to take place during 22015.  Construction is currently scheduled to start in 2016.



29) Grange Hall Road Culvert Replacement

Project Description: The project will generally consist of the replacement of the culvert approximately 0.25 miles north of the Grange Hall Road and Indian Ripple Road intersection.  The project will also install new guardrail.

Funding: Construction = $40,000 (Local/Total)

Status: The project is currently scheduled to begin construction in 2012.



30) Sunbeam Drive Culvert Replacement

Project Description: The project generally consists of the replacement of a deteriorated culvert on Sunbeam Drive.

Funding: Construction = $20,000 (Local/Total)

Status: The project is currently scheduled to begin construction in 2012.